Canary Wharf Contractors Canary Wharf Contractors
   
 
  Canary Wharf Contractors, Home Canary Wharf Contractors,Contact CWC Canary Wharf Group PLC
Canary Wharf Contractors, About Us
Canary Wharf Contractors, Canary Wharf Story
Canary Wharf Contractors, What We Have Built
Canary Wharf Contractors, Some Of Our Projects
Canary Wharf Contractors, Overcoming challenges
Canary Wharf Contractors, Health and Safety
Canary Wharf Contractors, Our services
Canary Wharf Contractors, New Projects
BP 3
BP 2
DS3 East
DS3 West
Drapers' Gardens
Riverside
Pan Peninsula
Crossharbour
Crossrail
Canary Wharf Contractors, Press Releases
Canary Wharf Contractors, Recruitment
Canary Wharf Contractors, Contact CWC
Disclaimer
     
  Canary Wharf Crossrail Station
   
 
FACTFILE

Completion: 2015
Number of Floors above water level; 3
Number of levels below water level; 4
256m long
27m – 30m wide
Base slab 25m below water level
310 Giken tubular piles
105 tension piles
30 plunge columns
156,000m 3 of excavated material
16,500 tonnes of reinforcement steel
156,000m 3 of concrete
Station Architect: Tony Meadows Associates
Landscape Architect: Gillespies
Station roof Architect Fosters and Partners.
Structural Engineer: Arup
M&E Services Engineer: Arup
Geotechnical Engineer: Arup
Principal Contractor: Canary Wharf Contractors
Client: Crossrail Ltd